1. Construction Attorney New York | Client Background and Construction Dispute Overview
Project Development and Contractual Framework
The client had acquired a parcel of land for the purpose of developing a mid scale lodging facility and entered into a written construction contract with the contractor for a fixed scope of work.
The agreement clearly defined the contract price, construction milestones, and payment schedule, but did not include any provision for separate management compensation or discretionary additional work without formal written approval.
2. Construction Attorney New York | Contractor’S Claims and Legal Exposure
Alleged Additional Work and Management Fees
The contractor argued that changes in construction conditions and informal communications justified additional compensation, despite the absence of written change orders or revised agreements.
The contractor further claimed that ongoing involvement in scheduling and coordination constituted a separate management engagement, even though no independent consulting or agency contract existed.
3. Construction Attorney New York | Defense Strategy against Construction Payment Claims
Rejection of Separate Compensation Agreement
The defense demonstrated that New York courts do not recognize implied management fee agreements in construction disputes absent express contractual language.
No written agreement, amendment, or contemporaneous correspondence supported the existence of a separate compensation arrangement, and generalized project involvement was shown to fall squarely within the contractor’s original contractual obligations.
No Proof of Approved Additional Construction Costs
The construction attorney New York further established that alleged additional work was neither authorized through written change orders nor reflected in contemporaneous billing records.
Under New York law, where a governing construction contract expressly requires written approval for scope changes, mere performance of additional work does not create an enforceable right to payment absent such approval, and the contractor’s after the fact assertions were insufficient to meet this standard.
4. Construction Attorney New York | Financial Record Analysis and Court Outcome
Court’S Findings and Complete Dismissal of Claims
The court concluded that no enforceable agreement supported the claimed management fees, that no valid approval existed for additional construction costs, and that the financial transfers could not be characterized as unpaid construction balances.
As a result, the court dismissed the contractor’s claims in their entirety and ordered the contractor to bear all litigation costs, fully vindicating the client’s position.
27 Jan, 2026

